portal_normal EE STRUCTURE orgcat: /PUBLICATIONS/EE-ECHO/NEWS

portal_normal PUBLICATION STRUCTURE cat: /publications/ee-echo/news

portal_normal CATEGORY STRUCTURE category: /PUBLICATIONS/EE-ECHO/NEWS

portal_normal STRUCTURE section: corknews

portal_normal getURLCurrent: /web/eveningecho/corknews/detailedstory?p_p_id=DetailedStory_WAR_portalsuite&p_p_lifecycle=0&_DetailedStory_WAR_portalsuite_arg_detailstory_uuid=b4867a04-ea55-4c7b-af7c-c07858ef543c

portal_normal getPortalURL getURLCurrent: http://admin-www.echolive.ie./web/eveningecho/corknews/detailedstory?p_p_id=DetailedStory_WAR_portalsuite&p_p_lifecycle=0&_DetailedStory_WAR_portalsuite_arg_detailstory_uuid=b4867a04-ea55-4c7b-af7c-c07858ef543c

portal_normal getPortalURL: http://admin-www.echolive.ie

portal_normal domain: http://admin-www.echolive.ie

STRUCTURE EE_062016_general_layout.tpl - url: /corknews/Mainline-wins-10-million-Swedish-wind-farm-contract-b4867a04-ea55-4c7b-af7c-c07858ef543c-ds

STRUCTURE EE_062016_general_layout.tpl - section: corknews

STRUCTURE EE_062016_general_layout.tpl - orgcat: orgcat = /PUBLICATIONS/EE-ECHO/NEWS

Mainline CEO Jamie O’Rourke.
Mainline CEO Jamie O’Rourke.
SOCIAL BOOKMARKS

Mainline wins €10 million Swedish wind farm contract

CORK-based company Mainline has signed a €10 million-plus contract to provide power and communication infrastructure to a major wind farm project in Sweden.

The work, to be carried out by Mainline on Europe’s largest onshore wind farm in the Markbygden Cluster, will involve project design to include installing more than 350 kilometres of MV power and fibre optic cabling.

Mainline CEO Jamie O’Rourke said Mainline will complete the work in less than 18 months, in challenging, and near-Arctic conditions for large parts of the year.

“We have just completed a smaller wind farm project inside the Arctic circle in Sweden, and this latest contract is our second significant project win in Sweden,” he said.

“Our ability to adapt our proven processes to Swedish requirements has been key to winning these projects in a very competitive commercial environment with local and international players in the market.” 

 Mainline CEO Jamie O’Rourke said Mainline will compete the work in less than 18 months. 

Mainline CEO Jamie O’Rourke said Mainline will compete the work in less than 18 months. 


Mr O’Rourke said that the construction, procurement and design teams in Mainline have proven themselves to be able to compete with the best.

He added that lessons learned in Sweden can be applied to major power infrastructural projects in the future back in Ireland.

Mainline is currently in the final stages of completing work on one of Europe’s largest onshore wind farms, Hästkullen, in the Nysäter wind park in Northern Sweden.

The project’s scope includes installing over 95 km’s of 36kV collector cable to 73 wind turbines, and all associated civil works over rugged mountainous terrain, using more than 450 linear kilometres of cable.

Mainline is also the lead electrical contractor on Dublin Airport’s €300 million-plus North Runway project, charged with building two new power sub-stations and installing over 2,000 runway, taxiway and approach lights, and more than 500 kilometres of power and fibre optic cabling.